Development at Kamarajar Port: Two new marine liquid terminals up next, 10 MTPA capacity envisaged

Kamarajar Port Ltd (KPL) has chalked out a plan to develop two more marine liquid terminals (MLT) as per phase III of its master plan at Kamarajar port.
8The combined capacity is pegged at 10 MTPA.
8Out of the two, one would be developed through the PPP mode and the other on a captive basis.
8One terminal will be built by IOCL on a  captive basis and the refiner will be commencing its construction by April 2016, completing it by the end of September 2018.
8Whereas the construction work for the second terminal will begin by April 2017 and is scheduled to completed by end of September 2019. 
8KPL has already awarded the construction, operation and maintenance of the marine liquid terminal (MLT) to Ennore Tank Terminals Pvt. Ltd on a 30 years build, operate and transfer (BOT) license.