Monday, 7 September 2015

Environmental clearance holds up two ONGC projects

Two ONGC projects held up because of lack of environment clearance.
8Jharia CBM block: The gas major is seeking extension of its TOR as it is going to expire on 09 th September, 2015.
8The extension is required as the compliance certificate of previous environmental clearance is yet to be obtained from the regional MoEF office in Ranchi which has delayed the project timeline.
8ONGC has also completed the public hearing for the Jharia CBM Block on  31.08.2015 and 04.09.2015 for Bokaro and Dhanbad districts respectively.
8Hence in view of above circumstances it is requested for the extension of TOR further by one year.
8Jorhat AAONN 2009/3 block: ONGC's plan to conduct three exploratory drilling wells in this block has been delayed again.
8Due to the delay in organizing public hearing by pollution control board of Assam the gas major has again requested the ministry to extend the TOR date by one year from 12.07.2015.

For more details visit indianpetroplus.com

No comments:

Post a Comment