Sunday, 6 September 2015

OIL plans 20 wells in Jaisalmer: Rs 96 crore to be spent

The total project cost is Rs 96 crore
8OIL ventured out of North East in the early eighties after its transition from a JV company to a national oil company. 
8The company discovered gas in the Jaisalmer sub-basin of the Tanot fields and heavy oil in the Bikaner- Nagaur sub-basin of Rajasthan basin in early nineties. 
8The Jaisalmer sub-basin is a pericratonic formation has a total area of 45,000 sq.km and the Bikaner-Nagaur basin of the intracratonic structure with an area of 70,000 sq. km.
8Total estimated drilling period  for each well is for 35-45 days
8Production testing for each Well will be be 10-15 days
8A water based mud system will be used in the wells
8The anticipated volume of drill cutting for each well will be around 150-200 m3

For more details visit indianpetroplus.com

No comments:

Post a Comment